I am familiar with @RISK for Project 4.1, and I like the feature of conditional branching. I see that @RISK 6 has probabilistic branching, but I want to branch based on logic, not chance. How can I do it?
In @RISK for Project 4.1, there was a wizard to set up conditional branching. Now it is much simpler: you just use an IF( ) function in Excel.
Make the Predecessors column visible in Project before importing your MPP file. That will cause @RISK to include it on the Tasks sheet at the time of importing.
If you have already imported your MPP file, you can add the Predecessors column without re-importing.
Apply an IF( ) function to the Predecessors cell for the task where you want to branch conditionally.
A minimal example is attached, to show the logic.
See also: Using a Risk Register is an alternative approach. In @RISK, click Help » Example Spreadsheets. Under Simulation with Microsoft Project, you'll find several examples with risk registers.
Additional keywords: If-Then branching