6.11. Tasks Not Linked in Gantt Chart

Applies to: @RISK 6.x/7.x, Professional and Industrial Editions

I opened my project in @RISK. It has predecessor-successor relationships, and the links show in Project, but the Gantt chart in Excel doesn't show any links between tasks. How do I make them appear?

There's a check box in the Gantt chart settings for @RISK.

  1. In @RISK, click Project » Charts and Reports » Standard Gantt to open the dialog.
  2. Tick (check) the box Display Links/Connectors Between Tasks.
  3. Click OK, and the connections will be drawn.